Blog

Embarking on a construction project, whether it’s a new home, a remodel or an addition, requires careful planning and a clear understanding of the construction timeline. Efficient project management not only ensures that your project stays on track but also helps in managing costs and expectations. Here’s a guide to understanding construction timelines and planning your project efficiently with general contractors in Omaha, NE.

1. Initial planning and design phase

Duration: 1-3 months

The first step in any construction project is the initial planning and design phase. This stage involves defining the scope of the project, setting a budget and hiring an architect or designer. During this phase, you will work closely with your designer to create blueprints and detailed plans that align with your vision and comply with local building codes.

Tip: Take your time during this phase to ensure that all your needs and preferences are reflected in the plans. Any changes made later in the process can cause significant delays.

2. Obtaining permits and approvals

Duration: 1-2 months

Once the plans are finalized, the next step is to obtain the necessary permits and approvals from local authorities. This process can vary in length depending on the complexity of the project and the specific regulations in your area. Delays in obtaining permits are common, so it’s crucial to factor this into your timeline.

Tip: Start the permitting process early and maintain open communication with local officials to expedite approvals.

3. Site preparation

Duration: 1-3 weeks

Site preparation includes clearing the land, grading and setting up temporary utilities. This phase also involves conducting any necessary environmental assessments and ensuring that the site is ready for construction.

Tip: Ensure that all preliminary site work is completed before construction begins to avoid interruptions.

4. Foundation and framing

Duration: 1-2 months

The foundation and framing stages are critical as they form the structural basis of your project. Laying the foundation typically involves excavation, pouring concrete and allowing it to cure. Framing follows, where the skeleton of the building is constructed.

Tip: Schedule inspections after the foundation and framing stages to ensure that everything is up to code before proceeding.

5. Mechanical, electrical and plumbing (MEP) work

Duration: 1-2 months

After the framing is complete, the next phase involves installing mechanical, electrical and plumbing systems. This stage requires coordination among various tradespeople to ensure that all systems are properly installed and integrated.

Tip: Regularly communicate with your contractors to keep the MEP work on schedule and resolve any issues promptly.

6. Interior and exterior finishes

Duration: 2-3 months

With the core systems in place, the project moves on to interior and exterior finishes. This includes drywall, flooring, cabinetry, painting, siding, roofing and landscaping. This phase significantly impacts the aesthetic and functional aspects of your project.

Tip: Order materials in advance to avoid delays due to supply chain issues.

7. Final inspections and walkthroughs

Duration: 1-2 weeks

Before the project is considered complete, final inspections must be conducted to ensure that all work complies with building codes and standards. After passing these inspections, a final walkthrough with your contractor will help identify any last-minute touch-ups or adjustments needed.

Tip: Create a checklist for the final walkthrough to ensure that no detail is overlooked.

General contractors in Omaha, NE

Efficiently planning your construction project timeline involves careful consideration of each phase and proactive management. By understanding the typical durations of each stage and planning accordingly, you can minimize delays and keep your project on track. Partnering with experienced professionals like Lightwine Construction can further ensure that your project is completed efficiently and to the highest standards. Ready to start planning your next construction project with general contractors in Omaha, NEContact us today for expert guidance and support.

Related Blogs

Why Winter Is the Perfect Time for Basement Renovations

When the colder months roll in, many homeowners shift their focus indoors, making winter the perfect time to tackle interior renovation projects. Among these, basement renovations stand out as a smart and strategic choice. Turning an underutilized ba...read more

How to Design an Outdoor Space You Can Use Year-Round

An outdoor living space that you can enjoy throughout all four seasons is the perfect blend of functionality, beauty, and comfort. Whether you’re hosting summer barbecues, cozying up by a fire in autumn, or sipping hot cocoa on a snowy winter eveni...read more

How to Keep Your Home Warm During Construction Projects in Winter

Undertaking construction projects in the winter can be challenging, especially when it comes to keeping your home warm. Whether you’re remodeling, adding a new room, or replacing windows, the cold weather and open spaces can lead to chilly interior...read more

Get an Estimate

What Our Clients Say

We take pride in every project we do because we want to like the work we do, not just you! Each project matters to us. Because of this, we aim to build a relationship with our clients so we can best make a project they can love and be excited about. Barebones communication is just not our style. Here at Lightwine Construction is able to both design and build a project. We sell what a project is going to look like.

We've engaged Lightwine Construction for several projects, initially discovering the company through the impeccable attention to detail and quality showcased in a friend's completed project. Our projects with Lightwine Construction involved fairly complex tasks, including framing and the restoration of the exterior of a 100-year-old residence. Johan and Heath's expertise, along with their valuable suggestions and problem-solving skills, played a crucial role in successfully completing these projects that other contractors had hesitated to undertake. We are pleased with the outstanding quality of work, attention to detail, and their ability to adhere to both schedule and budget. Without hesitation, we would highly recommend Lightwine Construction to friends and family.

— Mark and Brenda Ehrhart

I could not say more positive things about our experience with Lightwine Construction. From the very start of the process, Johann and Heath made us feel heard and respected. They were both communicative as well as trustworthy and their team was consistent and professional. When we changed our mind in the preliminary stages, they were very adaptable and encouraging. We most appreciated the details regarding all options, with both negative and positive aspects, allowing us to make the most appropriate decision. They came to our home personally on multiple occasions to ensure all was being taken care of and that we were happy with the ongoing stages as the vision came together. We built our addition towards the end of fall and in true Nebraska fashion, the snow came immediately. It is not only structurally amazing but it was a treat to be able to stand underneath our addition while the snow fell around us. We can’t wait to sit outside with our family and friends enjoying evening dinners, hosting summer birthday parties, and supporting Husker football. Experiencing all the seasons! I would recommend Lightwine Construction to everyone!

— Josh and Erika Marron

I hired Heath Lightwine last Spring to design and build an attached roof off my house into my backyard. He and his crew did a great job in a short amount of time. From the design to the last shingle going on, I couldn't have asked for better results! I will definitely hire Heath again.

— Don Shepard, Elkhorn